- State Fire Marshal (SFM) Inspections:
Most major projects will require two SFM
inspections.
- The first inspection shall occur prior to the placement of any hard surface finishes,
such as drywall, plaster, or hard ceilings, that would obscure any fire sprinkler piping
and related products.
- A final inspection is required prior to building occupancy. In order for a final
inspection to occur the following items must be complete:
- The fire alarm system is completely installed, tested, tagged, and certified in
accordance with NFPA 72 requirements.
- The fire sprinkler system is complete and has been hydrostatically tested, flushed and
tagged in accordance with NFPA 13.
- The fire pump installation is complete and the pump has been certified in accordance
with NFPA 20 requirements.
- All emergency and exit lights have been installed and tested.
- All fire doors, required exit hardware, magnetic door locks and latching hardware has
been installed and is in proper working order.
- All required emergency signage shall be installed.
- All portable fire extinguishers, pre-engineered fire suppression systems, and kitchen
hoods have been installed and inspected by the installing subcontractor.
- Scheduling of Inspections
:
- SFM Inspections:
- The University project manager shall call EH&S at 352 392-1904 to schedule the
inspection.
- Both of the SFM inspections and pump test must be scheduled at least 2 weeks prior to
the desired date of inspection. EH&S will coordinate the inspection with SFMs
office. The contractor is not permitted to schedule any SFM inspections directly with the
SFM.
- Hydrostatic testing of fire sprinkler piping:
- The project superintendent (or his representative) shall schedule all hydrostatic test
of both above and below ground piping by calling EH&S at 352 392-1904 at least 24
hours in advance.
- Underground piping shall be tested at 200 p.s.i. for 2 hours.
- Above ground piping shall be tested at 200 p.s.i. or 50 p.s.i. above normal operating
pressure whichever is greater for 2 hours with no visible leakage and 0 p.s.i. loss on the
test gauge.
- Properly filled out test papers are required at the conclusion of the test. It is the
responsibility of the contractor to maintain the test papers until they are given to the
SFM at the time of the final inspection.
- Authority Having Jurisdiction:
The authority having jurisdiction is the SFM. All
life safety issues shall be referred to EH&S directly. If desired and approved by the
project manager communication directly with the SFM shall be done in writing and EH&S
shall be copied on all correspondence.
- Project Changes:
All changes to the project must be approved by either EH&S or
the SFM. EH&S has been authorized to review all project changes and determine if they
must be submitted to the SFM for final approval. All proposed change orders shall be
submitted to EH&S by the architect at the time of issuance. EH&S will communicate
all review comments to the project manager in a timely manner. Costs associated with the
change order are not required and do not affect approval by EH&S.
- OSHA Compliance:
The contractor must strictly follow all OSHA construction safety
requirements, especially those sections as they apply to excavations, electrical safety,
and scaffolding. EH&S will offer advise to the contractor if request or complaints
received, but does not conduct construction site safety inspections.
- Job-site Accidents:
EH&S shall be notified of any job-site accidents that result
in serious personal injury. Serious personal injury is defined as an injury that requires
transportation to a hospital. Contact 352 392-1591, Extension 231.
- Test and Balance:
Notify EH&S of time and date of the Test and Balance
inspection.
- Fume Hoods:
Fume hoods shall be certified by EH&S prior to occupancy. Contact
Lab Safety at 352 846-2550.
- Portable Fire Extinguishers:
For installation of portable fire extinguishers contact
Fire Equipment Services at 352 392-2365.